Assessment Year | 1997 |
---|---|
Principal Product | Corrugated Containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
200,000
ft2
|
Annual Production | 840,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $261,035 | 4,687,866 |
kWh
|
$0.056 |
Electricity Demand | $24,900 | 9,528 |
kW-mo/yr
|
$2.61 |
Electricity Fees | $20,278 | - |
|
- |
Natural Gas | $193,444 | 45,207 |
MMBtu
|
$4.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $154,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,722 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $16,012 | $11,499 |
$13,116
240,621
kWh
|
$2,896
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,445 | $8,160 |
$5,279
97,011
kWh
|
$1,166
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,839 | $12 |
$1,506
27,550
kWh
|
$333
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,907 | $3,500 |
$2,002
36,635
kWh
|
$442
-
kW-mo/yr
|
- |
$(-537.0)
-
MMBtu
|
- | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $1,182 | $3,000 |
$891
16,413
kWh
|
$291
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,084 | $9,599 |
$2,270
41,618
kWh
|
$814
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $766 | $1,350 |
$637
11,723
kWh
|
$129
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $2,753 | - |
$2,255
41,325
kWh
|
$498
-
kW-mo/yr
|
- | - | - | - | |
09 | 3.4152: Carefully control water level in mass finishing equipment | $665 | - | - | - | - | - |
$665
-
Tgal
|
- | |
10 | 3.4113: Treat and reuse rinse waters | $940 | $500 | - | - | - | - |
$940
-
Tgal
|
- | |
11 | 2.8114: Change rate schedules or other changes in utility service | $25,407 | $200 | - | - | $25,407 | - | - | - | |
12 | 4.521: Clear and rent existing space | $93,500 | $750 | - | - | - | - | - | $93,500 | |
TOTAL RECOMMENDED | $154,500 | $38,570 |
$27,956
512,896
kWh
|
$6,569
-
kW-mo/yr
|
$25,407 |
$(-537.0)
-
MMBtu
|
$1,605
-
Tgal
|
$93,500 | ||
TOTAL IMPLEMENTED | $23,722 | $24,610 |
$17,783
326,202
kWh
|
$4,334
-
kW-mo/yr
|
- | - |
$1,605
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs