ITAC Assessment: AS0187
ITAC logo
ITAC Assessment: AS0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Bottled Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 300,000
ft2
Annual Production 15,000,000
pieces
Production Hrs. Annual 8,568
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $328,761 4,690,504
kWh
Electricity Demand $84,906 10,865
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $111,769 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,311

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 2.2622: Replace existing chiller with high efficiency model $81,742 $70,000 $54,846
783,705
kWh
$26,896
-
kW-mo/yr
-
02 2.7232: Replace existing hvac unit with high efficiency model $716 $1,750 $257
6,741
kWh
$459
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $7,717 $6,352 $6,303
89,977
kWh
$1,414
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,089 $1,421 $1,821
26,084
kWh
$268
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,677 - $1,677
24,033
kWh
- -
06 3.4113: Treat and reuse rinse waters $17,828 $1,300 - - $17,828
-
Tgal
TOTAL RECOMMENDED $111,769 $80,823 $64,904
930,540
kWh
$29,037
-
kW-mo/yr
$17,828
-
Tgal
TOTAL IMPLEMENTED $29,311 $9,073 $9,801
140,094
kWh
$1,682
-
kW-mo/yr
$17,828
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs