| Assessment Year | 1995 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $1 M to 5M |
| # of Employees | 70 |
| Plant Area |
20,000
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 5,252
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $87,937 | 987,397 |
kWh
|
$0.089 |
| Natural Gas | $5,158 | 854 |
MMBtu
|
$6.04 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,541 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,305 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $697 | $300 |
$697
7,913
kWh
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,836 | $1,706 |
$1,836
20,516
kWh
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $163 | - |
$163
1,758
kWh
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $992 | $2,275 |
$1,266
14,068
kWh
|
$(-274.0)
-
MMBtu
|
|
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $2,091 | $9,000 |
$2,091
23,447
kWh
|
- | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $1,608 | - |
$1,608
18,171
kWh
|
- | |
| 07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $154 | $750 |
$154
1,758
kWh
|
- | |
| TOTAL RECOMMENDED | $7,541 | $14,031 |
$7,815
87,631
kWh
|
$(-274.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,305 | $300 |
$2,305
26,084
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs