Assessment Year | 1994 |
---|---|
Principal Product | Precious Metal Plates |
NAICS |
n/a
|
SIC | 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
22,200
ft2
|
Annual Production | 200,000
lb
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,522 | 2,634,818 |
kWh
|
$0.076 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,313 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,856 | $4,686 |
$3,856
50,410
kWh
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,094 | - |
$1,094
14,361
kWh
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,242 | $400 |
$2,242
29,308
kWh
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $426 | $1,260 |
$426
5,569
kWh
|
|
05 | 2.2511: Insulate bare equipment | $370 | $75 |
$370
4,982
kWh
|
|
06 | 2.7232: Replace existing hvac unit with high efficiency model | $9,540 | $22,350 |
$9,540
124,853
kWh
|
|
07 | 2.7241: Install outside air damper / economizer on hvac unit | $4,565 | $5,200 |
$4,565
59,789
kWh
|
|
08 | 2.7122: Disconnect ballasts | $242 | $200 |
$242
3,224
kWh
|
|
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,874 | $8,097 |
$11,874
155,334
kWh
|
|
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $314 | $220 |
$314
4,103
kWh
|
|
TOTAL RECOMMENDED | $34,523 | $42,488 |
$34,523
451,933
kWh
|
||
TOTAL IMPLEMENTED | $12,313 | $10,706 |
$12,313
161,195
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs