Assessment Year | 1993 |
---|---|
Principal Product | AL AND MG CASTINGS |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 229
ton
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $159,168 | 1,952,814 |
kWh
|
$0.082 |
Natural Gas | $63,178 | 14,251 |
MMBtu
|
$4.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,906 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,210 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,799 | $992 | - |
$1,799
-
MMBtu
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,024 | $2,200 |
$1,024
12,603
kWh
|
- | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,461 | $1,500 |
$5,461
67,116
kWh
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $2,431 | $7,164 |
$1,094
13,482
kWh
|
- | $1,337 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,155 | $1,200 |
$8,155
100,234
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $381 | - |
$381
4,689
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $213 | $519 |
$213
2,638
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $379 | $1,598 |
$379
4,689
kWh
|
- | - | |
09 | 2.7144: Install spectral reflectors / delamp | $1,977 | $7,011 |
$1,977
24,326
kWh
|
- | - | |
10 | 2.8114: Change rate schedules or other changes in utility service | $7,086 | $50,250 |
$7,086
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $28,906 | $72,434 |
$25,770
229,777
kWh
|
$1,799
-
MMBtu
|
$1,337 | ||
TOTAL IMPLEMENTED | $14,210 | $3,219 |
$14,210
174,677
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs