| Assessment Year | 1992 |
|---|---|
| Principal Product | PRECISION METAL GOODS |
| NAICS |
n/a
|
| SIC | 3451: Screw Machine Products |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
n/a
|
| Annual Production | 400,000,000
pieces
|
| Production Hrs. Annual | 5,720
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $140,030 | 2,149,472 |
kWh
|
$0.065 |
| Natural Gas | $3,597 | 448 |
MMBtu
|
$8.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,104 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,164 | $10,246 |
$4,274
65,651
kWh
|
$(-110.0) | |
| 02 | 2.4133: Use most efficient type of electric motors | $746 | $5,150 |
$746
11,430
kWh
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,671 | - |
$1,671
25,791
kWh
|
- | |
| 04 | 2.7233: Use properly designed and sized hvac equipment | $1,658 | $64,750 |
$1,658
25,498
kWh
|
- | |
| 05 | 2.7226: Use computer programs to optimize hvac performance | $9,990 | $7,000 |
$9,990
153,283
kWh
|
- | |
| 06 | 2.7422: Plant trees or shrubs near windows to shield from sunlight | $1,369 | $3,500 |
$1,369
21,102
kWh
|
- | |
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $3,801 | - |
$3,801
58,324
kWh
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $250 | $50 |
$250
3,810
kWh
|
- | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,455 | $500 |
$2,455
37,808
kWh
|
- | |
| TOTAL RECOMMENDED | $26,104 | $91,196 |
$26,214
402,697
kWh
|
$(-110.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs