| Assessment Year | 1992 |
|---|---|
| Principal Product | PORTLAND CEMENT |
| NAICS |
n/a
|
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
n/a
|
| Annual Production | 700,000
ton
|
| Production Hrs. Annual | 8,234
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $5,100,141 | 91,808,032 |
kWh
|
$0.056 |
| Coal | $4,657,858 | 6,803,911 |
MMBtu
|
$0.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $837,754 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $837,754 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $3,012 | $24,872 |
$3,012
54,220
kWh
|
- | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $345,320 | $530,000 |
$345,320
6,216,589
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,583 | $8,109 |
$2,774
49,824
kWh
|
- | $(-191.0) | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,446 | $3,248 |
$1,446
26,084
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,462 | $7,288 |
$4,462
80,305
kWh
|
- | - | |
| 06 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $236,795 | $750,000 |
$324,395
5,839,977
kWh
|
- | $(-87,600.0) | |
| 07 | 2.8113: Purchase gas directly from a contract gas supplier | $107,027 | $6,700 | - |
$107,027
-
MMBtu
|
- | |
| 08 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $129,176 | $640,000 |
$364,057
6,547,186
kWh
|
$(-169,409.0)
-
MMBtu
|
$(-65,472.0) | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,933 | $2,000 |
$7,933
142,732
kWh
|
- | - | |
| TOTAL RECOMMENDED | $837,754 | $1,972,217 |
$1,053,399
18,956,917
kWh
|
$(-62,382.0)
-
MMBtu
|
$(-153,263.0) | ||
| TOTAL IMPLEMENTED | $837,754 | $1,972,217 |
$1,053,399
18,956,917
kWh
|
$(-62,382.0)
-
MMBtu
|
$(-153,263.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs