| Assessment Year | 1991 |
|---|---|
| Principal Product | WOOD PALLETS |
| NAICS |
n/a
|
| SIC | 2448: Wood Pallets and Skids |
| Sales Range | $1 M to 5M |
| # of Employees | 30 |
| Plant Area |
n/a
|
| Annual Production | 13,000
thousand feet
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $22,485 | 227,726 |
kWh
|
$0.099 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,898 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,032 | $500 |
$3,032
30,774
kWh
|
- | |
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,446 | $1,200 |
$4,446
45,135
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $572 | - |
$572
5,862
kWh
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $296 | $965 |
$296
2,931
kWh
|
- | |
| 05 | 2.4312: Improve lubrication practices | $706 | - |
$706
7,034
kWh
|
- | |
| 06 | 2.8114: Change rate schedules or other changes in utility service | $1,584 | $5,000 |
$1,584
-
kWh
|
- | |
| 07 | 2.3191: Use demand controller or load shedder | $110 | $80 |
$110
-
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $87 | - |
$134
1,465
kWh
|
$(-47.0) | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $65 | $39 |
$65
586
kWh
|
- | |
| TOTAL RECOMMENDED | $10,898 | $7,784 |
$10,945
93,787
kWh
|
$(-47.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs