ITAC Assessment: AS0035
ITAC logo
ITAC Assessment: AS0035
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product STRUCTURAL STEEL
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 110,000
ton
Production Hrs. Annual 5,460
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,224 891,559
kWh
LPG $2,805 290
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,088 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,088

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $495 $698 $495
6,155
kWh
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $265 - $265
3,224
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,203 $1,000 $17,203
215,416
kWh
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,320 $40 $1,320
16,413
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $641 $75 $641
7,913
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $164 $324 $164
2,052
kWh
TOTAL RECOMMENDED $20,088 $2,137 $20,088
251,173
kWh
TOTAL IMPLEMENTED $20,088 $2,137 $20,088
251,173
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs