ITAC Assessment: AS0016
ITAC logo
ITAC Assessment: AS0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product CEMENT BLOCKS
NAICS
n/a
SIC 3271: Concrete Block and Brick
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area
n/a
Annual Production 30,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $205,128 2,935,522
kWh
Natural Gas $76,459 25,225
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,851 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,851

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,345 $1,000 $5,345
76,495
kWh
-
02 2.4239: Eliminate or reduce compressed air usage $6,716 $1,200 $6,716
96,131
kWh
-
03 2.2136: Install / repair insulation on steam lines $397 $536 - $397
-
MMBtu
04 2.2135: Repair and eliminate steam leaks $2,612 $200 - $2,612
-
MMBtu
05 2.2511: Insulate bare equipment $8,146 $6,624 - $8,146
-
MMBtu
06 2.4133: Use most efficient type of electric motors $790 $1,580 $790
11,430
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,845 - $1,845
26,377
kWh
-
TOTAL RECOMMENDED $25,851 $11,140 $14,696
210,433
kWh
$11,155
-
MMBtu
TOTAL IMPLEMENTED $25,851 $11,140 $14,696
210,433
kWh
$11,155
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs