ITAC Assessment: AR0197
ITAC logo
ITAC Assessment: AR0197
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Sawmill Equipment
NAICS
n/a
SIC 3553: Woodworking Machinery
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area 150,000
ft2
Annual Production 350
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,436 1,401,524
kWh
Electricity Demand $42,446 2,822
kW-mo/yr
Natural Gas $19,658 3,235
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,118 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,457 $2,178 $809
25,205
kWh
$648
-
kW-mo/yr
- - -
02 2.7122: Disconnect ballasts $6,341 $2,605 $3,568
108,441
kWh
$2,773
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $26 - $14
586
kWh
$12
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $101 $1,780 $56
1,758
kWh
$45
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,334 $6,713 $981
30,774
kWh
$1,353
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,153 $120 $779
24,326
kWh
$374
-
kW-mo/yr
- - -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $7,335 $500 - - $827
-
Tgal
$6,508 -
08 4.653: Maintain/enlarge a stock of spare parts $80,371 $16,150 - - - - $80,371
TOTAL RECOMMENDED $99,118 $30,046 $6,207
191,090
kWh
$5,205
-
kW-mo/yr
$827
-
Tgal
$6,508 $80,371
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs