| Assessment Year | 2000 |
|---|---|
| Principal Product | Steel Forgings |
| NAICS |
n/a
|
| SIC | 3462: Iron and Steel Forgings |
| Sales Range | $5 M to 10M |
| # of Employees | 85 |
| Plant Area |
186,000
ft2
|
| Annual Production | 600,000
pieces
|
| Production Hrs. Annual | 5,787
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $229,941 | 6,220,985 |
kWh
|
$0.037 |
| Electricity Demand | $208,476 | 23,678 |
kW-mo/yr
|
$8.80 |
| Natural Gas | $404,499 | 143,645 |
MMBtu
|
$2.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $301,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $77,452 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $916 | $1,360 |
$586
15,826
kWh
|
$330
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $351 | - |
$225
6,155
kWh
|
$126
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $496 | $180 |
$252
6,741
kWh
|
$244
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,868 | $130 |
$8,095
218,933
kWh
|
$3,773
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.2442: Preheat combustion air with waste heat | $60,765 | $150,000 | - | - |
$60,765
-
MMBtu
|
- | - | - | |
| 06 | 3.4154: Eliminate leaks in water lines and valves | $4,468 | $175 | - | - | - |
$4,468
-
Tgal
|
- | - | |
| 07 | 3.1191: Change procedures / equipment / operating conditions | $222,939 | $244,000 | - | - |
$64,818
-
MMBtu
|
- |
$89,910
-
lb
|
$68,211 | |
| TOTAL RECOMMENDED | $301,803 | $395,845 |
$9,158
247,655
kWh
|
$4,473
-
kW-mo/yr
|
$125,583
-
MMBtu
|
$4,468
-
Tgal
|
$89,910
-
lb
|
$68,211 | ||
| TOTAL IMPLEMENTED | $77,452 | $150,305 |
$8,320
225,088
kWh
|
$3,899
-
kW-mo/yr
|
$60,765
-
MMBtu
|
$4,468
-
Tgal
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs