Assessment Year | 2000 |
---|---|
Principal Product | Steel Fabrication |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | n/a |
# of Employees | 140 |
Plant Area |
78,000
ft2
|
Annual Production | 31,200,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,042 | 1,192,556 |
kWh
|
$0.029 |
Electricity Demand | $41,011 | 3,933 |
kW-mo/yr
|
$10.43 |
Natural Gas | $6,095 | 1,252 |
MMBtu
|
$4.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,083 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,531 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $368 | $340 |
$312
1,172
kWh
|
$56
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,363 | $500 |
$2,834
97,890
kWh
|
$3,529
-
kW-mo/yr
|
- | - | |
03 | 3.5111: Filter and reuse hydraulic oil | $3,552 | $1,500 | - | - |
$3,552
-
Tgal
|
- | |
04 | 4.425: Eliminate/reduce redundant inspections | $23,800 | $16,000 | - | - | - | $23,800 | |
TOTAL RECOMMENDED | $34,083 | $18,340 |
$3,146
99,062
kWh
|
$3,585
-
kW-mo/yr
|
$3,552
-
Tgal
|
$23,800 | ||
TOTAL IMPLEMENTED | $30,531 | $16,840 |
$3,146
99,062
kWh
|
$3,585
-
kW-mo/yr
|
- | $23,800 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs