Assessment Year | 1999 |
---|---|
Principal Product | Boat Building |
NAICS |
n/a
|
SIC | 3732: Boat Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
70,025
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,987 | 710,727 |
kWh
|
$0.055 |
Electricity Demand | $7,322 | 3,635 |
kW-mo/yr
|
$2.01 |
Natural Gas | $18,520 | 3,711 |
MMBtu
|
$4.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,932 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $142 | - |
$122
1,758
kWh
|
$20
-
kW-mo/yr
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $993 | $153 | - | - |
$993
-
MMBtu
|
- | - | |
03 | 3.2176: Increase use of automation | $5,548 | $8,000 | - | - | - |
$5,548
-
lb
|
- | |
04 | 3.2176: Increase use of automation | $1,249 | $3,000 | - | - | - | - | $1,249 | |
TOTAL RECOMMENDED | $7,932 | $11,153 |
$122
1,758
kWh
|
$20
-
kW-mo/yr
|
$993
-
MMBtu
|
$5,548
-
lb
|
$1,249 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs