ITAC Assessment: AR0175
ITAC logo
ITAC Assessment: AR0175
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Boat Building
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 70,025
ft2
Annual Production 12,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,987 710,727
kWh
Electricity Demand $7,322 3,635
kW-mo/yr
Natural Gas $18,520 3,711
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,932 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $142 - $122
1,758
kWh
$20
-
kW-mo/yr
- - -
02 2.2437: Recover waste heat from equipment $993 $153 - - $993
-
MMBtu
- -
03 3.2176: Increase use of automation $5,548 $8,000 - - - $5,548
-
lb
-
04 3.2176: Increase use of automation $1,249 $3,000 - - - - $1,249
TOTAL RECOMMENDED $7,932 $11,153 $122
1,758
kWh
$20
-
kW-mo/yr
$993
-
MMBtu
$5,548
-
lb
$1,249
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs