Assessment Year | 1999 |
---|---|
Principal Product | Baseball and Military hats |
NAICS |
n/a
|
SIC | 2353: Hats, Caps, and Millinery |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
61,200
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 1,800
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,116 | 518,171 |
kWh
|
$0.052 |
Electricity Demand | $5,369 | 2,261 |
kW-mo/yr
|
$2.37 |
Natural Gas | $18,405 | 3,835 |
MMBtu
|
$4.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,986 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $158 | $238 | - | - |
$158
-
MMBtu
|
- | - | |
02 | 2.7135: Install occupancy sensors | $74 | $120 |
$55
1,172
kWh
|
$19
-
kW-mo/yr
|
- | - | - | |
03 | 3.4151: Minimize water usage | $352 | $900 |
$(-44.0)
(-879)
kWh
|
- |
$195
-
MMBtu
|
$201
-
Tgal
|
- | |
04 | 4.652: Replace existing equipment with more suitable substitutes | $6,802 | $8,767 | - | - | - | - | $6,802 | |
05 | 4.131: Modify process to reduce material use/cost | $9,600 | $1,000 | - | - | - | - | $9,600 | |
TOTAL RECOMMENDED | $16,986 | $11,025 |
$11
293
kWh
|
$19
-
kW-mo/yr
|
$353
-
MMBtu
|
$201
-
Tgal
|
$16,402 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs