ITAC Assessment: AR0172
ITAC logo
ITAC Assessment: AR0172
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Baseball and Military hats
NAICS
n/a
SIC 2353: Hats, Caps, and Millinery
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 61,200
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 1,800
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,116 518,171
kWh
Electricity Demand $5,369 2,261
kW-mo/yr
Natural Gas $18,405 3,835
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,986 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings
01 2.2136: Install / repair insulation on steam lines $158 $238 - - $158
-
MMBtu
- -
02 2.7135: Install occupancy sensors $74 $120 $55
1,172
kWh
$19
-
kW-mo/yr
- - -
03 3.4151: Minimize water usage $352 $900 $(-44.0)
(-879)
kWh
- $195
-
MMBtu
$201
-
Tgal
-
04 4.652: Replace existing equipment with more suitable substitutes $6,802 $8,767 - - - - $6,802
05 4.131: Modify process to reduce material use/cost $9,600 $1,000 - - - - $9,600
TOTAL RECOMMENDED $16,986 $11,025 $11
293
kWh
$19
-
kW-mo/yr
$353
-
MMBtu
$201
-
Tgal
$16,402
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs