Assessment Year | 1997 |
---|---|
Principal Product | Ladies Casual and Dress Shoes |
NAICS |
n/a
|
SIC | 3144: Women's Footwear, Except Athletic |
Sales Range | $1 M to 5M |
# of Employees | 265 |
Plant Area |
30,000
ft2
|
Annual Production | 138,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,754 | 1,298,066 |
kWh
|
$0.035 |
Electricity Demand | $61,597 | 4,407 |
kW-mo/yr
|
$13.98 |
Natural Gas | $7,537 | 1,508 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $101,385 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,853 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $562 | $234 |
$216
6,155
kWh
|
$346
-
kW-mo/yr
|
- | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $559 | $402 |
$210
5,862
kWh
|
$349
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $33 | $95 |
$10
293
kWh
|
$23
-
kW-mo/yr
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $107 | - |
$32
879
kWh
|
$75
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,845 | $220 |
$543
15,533
kWh
|
$1,302
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $136 | $60 |
$40
1,172
kWh
|
$96
-
kW-mo/yr
|
- | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $110 | $100 |
$110
3,224
kWh
|
- | - | - | - | |
08 | 2.7314: Reduce ventilation air | $1,309 | $400 |
$1,309
71,805
kWh
|
- | - | - | - | |
09 | 3.4115: Recover and reuse cooling water | $1,536 | $3,400 | - | - |
$1,536
-
Tgal
|
- | - | |
10 | 3.1192: Reduce scrap production | $14,060 | $3,000 | - | - | - |
$4,700
-
lb
|
$9,360 | |
11 | 4.514: Re-arrange equipment layout to reduce handling costs | $55,352 | $355,000 |
$(-808.0)
(-6,741)
kWh
|
- | - | - | $56,160 | |
12 | 4.515: Install shelves / racks to utilize unused space | $25,776 | $16,800 | - | - | - |
$10,800
-
lb
|
$14,976 | |
TOTAL RECOMMENDED | $101,385 | $379,711 |
$1,662
98,182
kWh
|
$2,191
-
kW-mo/yr
|
$1,536
-
Tgal
|
$15,500
-
lb
|
$80,496 | ||
TOTAL IMPLEMENTED | $3,853 | $1,117 |
$2,104
94,372
kWh
|
$1,749
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs