Assessment Year | 2025 |
---|---|
Principal Product | Sheet metal formed parts, precision milled and turned parts, wire and sinker EDM services, welded fabrications, plastic injection molded parts and powder coating |
NAICS | 333999: All Other Miscellaneous General Purpose Machinery Manufacturing |
SIC | 3523: Farm Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
43,000
ft2
|
Annual Production | 515,000
units
|
Production Hrs. Annual | 4,118
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $67,910 | 1,151,830 |
kWh
|
$0.059 | |
Electricity Demand | $40,494 | 3,961 |
kW-mo/yr
|
$10.22 | |
LPG | $3,720 | 128 |
MMBtu
|
$28.97 | |
Waste Disposal Costs | |||||
Water Usage | $2,842 | 431 |
Tgal
|
$6.59 | |
TOTAL YEARLY COSTS | $114,966 | ||||
RECOMMENDED SAVINGS* | $73,253 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $31,215 | $3,595,220 |
$31,215
529,076
kWh
|
- | - | |
02 | 2.7232: Replace existing hvac unit with high efficiency model | $11,689 | $569,500 |
$1,231
20,862
kWh
|
$458
-
kW-mo/yr
|
$10,000 | |
03 | 2.4322: Use or replace with energy efficient substitutes | $11,683 | $5,100 |
$11,683
198,020
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,290 | $32,500 |
$4,520
76,570
kWh
|
$1,770
-
kW-mo/yr
|
- | |
05 | 2.3212: Optimize plant power factor | $1,376 | $3,623 | - |
$1,376
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $275 | $480 |
$275
4,660
kWh
|
- | - | |
07 | 2.8121: Apply for tax-free status for energy purchases | $10,725 | - | - | - | $10,725 | |
TOTAL RECOMMENDED | $73,253 | $4,206,423 |
$48,924
829,188
kWh
|
$3,604
-
kW-mo/yr
|
$20,725 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs