Assessment Year | 2025 |
---|---|
Principal Product | Plastic Bottles |
NAICS | 326160: Plastics Bottle Manufacturing |
SIC | 3085: Plastics Bottles |
Sales Range | $10 M to 50M |
# of Employees | 165 |
Plant Area |
75,000
ft2
|
Annual Production | 90,000,000
pieces
|
Production Hrs. Annual | 8,230
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $780,660 | 19,601,806 |
kWh
|
$0.040 | |
Electricity Demand | $497,988 | 41,650 |
kW-mo/yr
|
$11.96 | |
Electricity Fees | $8,133 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $86,123 | 6,937 |
Tgal
|
$12.42 | |
TOTAL YEARLY COSTS | $1,372,904 | ||||
RECOMMENDED SAVINGS* | $281,902 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $104,000 | $115,000 | - |
$104,000
-
kW-mo/yr
|
- | |
02 | 2.2622: Replace existing chiller with high efficiency model | $62,000 | $644,000 |
$37,500
938,000
kWh
|
$24,500
-
kW-mo/yr
|
- | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $45,840 | $1,490 | - | - |
$45,840
-
Tgal
|
|
04 | 2.4321: Upgrade obsolete equipment | $35,490 | $397,200 |
$21,330
546,870
kWh
|
$14,160
-
kW-mo/yr
|
- | |
05 | 2.4321: Upgrade obsolete equipment | $26,345 | $418,850 |
$15,507
397,633
kWh
|
$10,838
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,227 | $30,000 |
$8,227
206,192
kWh
|
- | - | |
TOTAL RECOMMENDED | $281,902 | $1,606,540 |
$82,564
2,088,695
kWh
|
$153,498
-
kW-mo/yr
|
$45,840
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs