ITAC Assessment: AM0932
ITAC logo
ITAC Assessment: AM0932
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Elementary School Students
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $1
M
to 5
M
# of Employees 70
Plant Area 63,237
ft2
Annual Production 100
units
Production Hrs. Annual 3,395
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,010 605,524
kWh
Natural Gas $5,051 449
MMBtu
TOTAL YEARLY COSTS $28,061
RECOMMENDED SAVINGS* $25,405 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.5123: Reduce fluid flow rates $1,346 $1,000 $1,346
35,430
kWh
-
02 2.7135: Install occupancy sensors $163 $4,120 $163
4,300
kWh
-
03 2.9114: Use solar heat to make electricty $22,931 $624,000 $22,931
603,446
kWh
-
04 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $965 $29,671 $268
7,065
kWh
$697
-
MMBtu
TOTAL RECOMMENDED $25,405 $658,791 $24,708
650,241
kWh
$697
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs