ITAC Assessment: AM0914
ITAC logo
ITAC Assessment: AM0914
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal heat treating
NAICS 332811: Metal Heat Treating
SIC 3398: Metal Heat Treating
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 75,600
ft2
Annual Production 12,000,000
lb
Production Hrs. Annual 6,624
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $215,273 4,535,352
kWh
Electricity Demand $201,431 16,803
kW-mo/yr
Electricity Fees $13,288 -
Natural Gas $703,797 100,210
MMBtu
TOTAL YEARLY COSTS $1,133,789
RECOMMENDED SAVINGS* $45,735 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $40,720 $77,840 - $40,720
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,190 $2,260 $1,350
28,670
kWh
$780
-
kW-mo/yr
$60
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,515 - $1,020
21,640
kWh
$495
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,310 - $1,310
27,920
kWh
- -
TOTAL RECOMMENDED $45,735 $80,100 $3,680
78,230
kWh
$41,995
-
kW-mo/yr
$60
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs