ITAC Assessment: AM0904
ITAC logo
ITAC Assessment: AM0904
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Elementary School Students
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 81,500
ft2
Annual Production 100
units
Production Hrs. Annual 3,402
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,515 583,680
kWh
Electricity Demand $41,431 3,133
kW-mo/yr
Natural Gas $10,526 1,044
MMBtu
TOTAL YEARLY COSTS $76,472
RECOMMENDED SAVINGS* $27,516 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $5,834 $2,000 $3,644
86,767
kWh
- $2,190
-
MMBtu
02 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $6,987 $228,463 $4,093
97,456
kWh
- $2,894
-
MMBtu
03 2.9114: Use solar heat to make electricty $14,695 $311,855 $12,540
298,581
kWh
$2,155
-
kW-mo/yr
-
TOTAL RECOMMENDED $27,516 $542,318 $20,277
482,804
kWh
$2,155
-
kW-mo/yr
$5,084
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs