Assessment Year | 2023 |
---|---|
Principal Product | Metal stampings |
NAICS | 336370: Motor Vehicle Metal Stamping |
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
68,000
ft2
|
Annual Production | 22,000,000
lb
|
Production Hrs. Annual | 4,890
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,499 | 1,575,308 |
kWh
|
$0.053 |
Electricity Demand | $48,797 | 5,983 |
kW-mo/yr
|
$8.16 |
Electricity Fees | $4,410 | - |
|
- |
TOTAL YEARLY COSTS | $136,706 | |||
RECOMMENDED SAVINGS* | $19,392 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,442 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,830 | $1,000 |
$4,980
93,900
kWh
|
$1,850
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,300 | - |
$3,130
59,000
kWh
|
$1,170
-
kW-mo/yr
|
- | |
03 | 2.2533: Replace air curtain doors with solid doors | $3,790 | $8,650 |
$3,790
71,510
kWh
|
- | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $1,360 | $303 |
$1,360
25,650
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,340 | $850 |
$830
15,570
kWh
|
$510
-
kW-mo/yr
|
- | |
06 | 2.4314: Use synthetic lubricant | $860 | $440 |
$530
9,930
kWh
|
$330
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $912 | $1,783 |
$655
12,355
kWh
|
$240
-
kW-mo/yr
|
$17 | |
TOTAL RECOMMENDED | $19,392 | $13,026 |
$15,275
287,915
kWh
|
$4,100
-
kW-mo/yr
|
$17 | ||
TOTAL IMPLEMENTED | $10,442 | $3,936 |
$7,825
147,475
kWh
|
$2,600
-
kW-mo/yr
|
$17 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs