ITAC Assessment: AM0887
ITAC logo
ITAC Assessment: AM0887
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Metal stampings
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 68,000
ft2
Annual Production 22,000,000
lb
Production Hrs. Annual 4,890
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,499 1,575,308
kWh
Electricity Demand $48,797 5,983
kW-mo/yr
Electricity Fees $4,410 -
TOTAL YEARLY COSTS $136,706
RECOMMENDED SAVINGS* $19,392 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,442

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,830 $1,000 $4,980
93,900
kWh
$1,850
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,300 - $3,130
59,000
kWh
$1,170
-
kW-mo/yr
-
03 2.2533: Replace air curtain doors with solid doors $3,790 $8,650 $3,790
71,510
kWh
- -
04 2.4322: Use or replace with energy efficient substitutes $1,360 $303 $1,360
25,650
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,340 $850 $830
15,570
kWh
$510
-
kW-mo/yr
-
06 2.4314: Use synthetic lubricant $860 $440 $530
9,930
kWh
$330
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $912 $1,783 $655
12,355
kWh
$240
-
kW-mo/yr
$17
TOTAL RECOMMENDED $19,392 $13,026 $15,275
287,915
kWh
$4,100
-
kW-mo/yr
$17
TOTAL IMPLEMENTED $10,442 $3,936 $7,825
147,475
kWh
$2,600
-
kW-mo/yr
$17
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs