| Assessment Year | 2023 |
|---|---|
| Principal Product | dimensional lumber boards |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $5 M to 10M |
| # of Employees | 32 |
| Plant Area |
40,000
ft2
|
| Annual Production | 18,000
thousand feet
|
| Production Hrs. Annual | 2,008
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,278 | 1,227,019 |
kWh
|
$0.052 |
| Electricity Demand | $120,779 | 20,227 |
kW-mo/yr
|
$5.97 |
| Electricity Fees | $24,292 | - |
|
- |
| Natural Gas | $97,020 | 12,420 |
MMBtu
|
$7.81 |
| TOTAL YEARLY COSTS | $305,369 | |||
| RECOMMENDED SAVINGS* | $66,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $66,833 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $57,480 | $10,000 | - | - | $22,992 | $34,488 | |
| 02 | 2.8123: Pay utility bills on time | $3,361 | - | - | - | $3,361 | - | |
| 03 | 2.6218: Turn off equipment when not in use | $3,648 | - |
$3,648
71,255
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,971 | $1,000 |
$1,161
22,680
kWh
|
$810
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $67 | $152 |
$67
1,300
kWh
|
- | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $373 | $32 |
$199
3,886
kWh
|
$174
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $66,900 | $11,184 |
$5,075
99,121
kWh
|
$984
-
kW-mo/yr
|
$26,353 | $34,488 | ||
| TOTAL IMPLEMENTED | $66,833 | $11,032 |
$5,008
97,821
kWh
|
$984
-
kW-mo/yr
|
$26,353 | $34,488 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs