| Assessment Year | 2022 |
|---|---|
| Principal Product | Chemicals |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 130 |
| Plant Area |
150,000
ft2
|
| Annual Production | 200,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $380,567 | 9,718,573 |
kWh
|
$0.039 |
| Electricity Demand | $144,070 | 17,556 |
kW-mo/yr
|
$8.21 |
| Electricity Fees | $3,644 | - |
|
- |
| Natural Gas | $1,636,381 | 252,899 |
MMBtu
|
$6.47 |
| TOTAL YEARLY COSTS | $2,164,662 | |||
| RECOMMENDED SAVINGS* | $437,918 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $357,150 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $355,500 | $15,000 | - | - | - | - | $96,300 | $259,200 | |
| 02 | 2.2113: Repair or replace steam traps | $42,200 | $2,460 | - | - | - |
$42,200
-
MMBtu
|
- | - | |
| 03 | 2.2135: Repair and eliminate steam leaks | $28,000 | $4,920 | - | - | - |
$28,000
-
MMBtu
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $8,300 | $36,700 | - |
$8,300
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,210 | $40 |
$1,690
43,300
kWh
|
$520
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7132: Install timers on light switches in little used areas | $1,650 | $160 |
$1,025
26,300
kWh
|
$625
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.8114: Change rate schedules or other changes in utility service | $58 | - | - | - | $58 | - | - | - | |
| TOTAL RECOMMENDED | $437,918 | $59,280 |
$2,715
69,600
kWh
|
$9,445
-
kW-mo/yr
|
$58 |
$70,200
-
MMBtu
|
$96,300 | $259,200 | ||
| TOTAL IMPLEMENTED | $357,150 | $15,160 |
$1,025
26,300
kWh
|
$625
-
kW-mo/yr
|
- | - | $96,300 | $259,200 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs