Assessment Year | 2022 |
---|---|
Principal Product | doctor visits |
NAICS | 621111: Offices of Physicians (except Mental Health Specialists) |
SIC | 8011: Offices and Clinics of Doctors of Medicine |
Sales Range | $5 M to 10M |
# of Employees | 150 |
Plant Area |
128,961
ft2
|
Annual Production | 5,000
pieces
|
Production Hrs. Annual | 4,300
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $79,847 | 2,079,360 |
kWh
|
$0.038 |
Electricity Demand | $71,283 | 5,534 |
kW-mo/yr
|
$12.88 |
TOTAL YEARLY COSTS | $151,130 | |||
RECOMMENDED SAVINGS* | $48,698 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,075 | $110,044 |
$16,005
416,798
kWh
|
$18,070
-
kW-mo/yr
|
|
02 | 2.7224: Reduce space conditioning during non-working hours | $8,689 | $45,000 |
$3,814
99,355
kWh
|
$4,875
-
kW-mo/yr
|
|
03 | 2.7221: Lower temperature during the winter season and vice-versa | $2,243 | $11,600 |
$1,529
39,809
kWh
|
$714
-
kW-mo/yr
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,656 | $8,400 |
$1,656
43,133
kWh
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,035 | $10,000 |
$2,035
52,997
kWh
|
- | |
TOTAL RECOMMENDED | $48,698 | $185,044 |
$25,039
652,092
kWh
|
$23,659
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs