| Assessment Year | 2022 |
|---|---|
| Principal Product | Hot dog and Hamburger Buns |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
137,000
ft2
|
| Annual Production | 500,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $373,062 | 7,206,939 |
kWh
|
$0.052 |
| Electricity Demand | $123,084 | 16,780 |
kW-mo/yr
|
$7.34 |
| Electricity Fees | $54,157 | - |
|
- |
| Natural Gas | $258,994 | 51,069 |
MMBtu
|
$5.07 |
| TOTAL YEARLY COSTS | $809,297 | |||
| RECOMMENDED SAVINGS* | $244,480 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $204,900 | $15,000 | - | - | $40,900 | - | - | - | $164,000 | |
| 02 | 2.3212: Optimize plant power factor | $16,640 | $31,840 | - |
$16,640
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.1241: Reduce excessive boiler blowdown | $4,554 | $3,000 | - | - | - |
$224
-
MMBtu
|
$4,330
-
Tgal
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,296 | $1,600 |
$9,150
176,000
kWh
|
$2,146
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $296 | $54 |
$226
4,344
kWh
|
$70
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,794 | $4,255 |
$6,280
120,680
kWh
|
$510
-
kW-mo/yr
|
- | - | - | $4 | - | |
| TOTAL RECOMMENDED | $244,480 | $55,749 |
$15,656
301,024
kWh
|
$19,366
-
kW-mo/yr
|
$40,900 |
$224
-
MMBtu
|
$4,330
-
Tgal
|
$4 | $164,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs