ITAC Assessment: AM0855
ITAC logo
ITAC Assessment: AM0855
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Conveyors
NAICS 333922: Conveyor and Conveying Equipment Manufacturing
SIC 3535: Conveyors and Conveying Equipment
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 120,000
ft2
Annual Production 3,500,000
ton
Production Hrs. Annual 3,050
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,311 760,037
kWh
Electricity Demand $37,440 3,877
kW-mo/yr
Electricity Fees $6,469 -
TOTAL YEARLY COSTS $85,220
RECOMMENDED SAVINGS* $48,632 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,370

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $32,345 $5,000 - - $6,469 $25,876
02 2.3212: Optimize plant power factor $7,487 $13,455 - $7,487
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,775 $2,575 $2,005
37,140
kWh
$1,770
-
kW-mo/yr
- -
04 2.6218: Turn off equipment when not in use $2,135 - $1,130
21,010
kWh
$1,005
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,650 $1,000 $880
16,240
kWh
$770
-
kW-mo/yr
- -
06 2.4239: Eliminate or reduce compressed air usage $830 $2,100 $830
15,340
kWh
- - -
07 2.7135: Install occupancy sensors $410 $1,085 $410
7,601
kWh
- - -
TOTAL RECOMMENDED $48,632 $25,215 $5,255
97,331
kWh
$11,032
-
kW-mo/yr
$6,469 $25,876
TOTAL IMPLEMENTED $37,370 $9,185 $3,250
60,191
kWh
$1,775
-
kW-mo/yr
$6,469 $25,876
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs