ITAC Assessment: AM0840
ITAC logo
ITAC Assessment: AM0840
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Industrial springs
NAICS 332613: Spring Manufacturing
SIC 3493: Steel Springs, Except Wire
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 100,000
ft2
Annual Production 25,000
pieces
Production Hrs. Annual 2,574
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,634 1,677,134
kWh
Electricity Demand $75,936 10,486
kW-mo/yr
Electricity Fees $4,739 -
Natural Gas $111,324 23,282
MMBtu
TOTAL YEARLY COSTS $268,633
RECOMMENDED SAVINGS* $49,446 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,201

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $20,260 $33,400 - $20,260
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,045 $17,675 $6,080
129,450
kWh
$7,300
-
kW-mo/yr
- $665
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,290 $1,000 $2,860
60,890
kWh
$3,430
-
kW-mo/yr
- -
04 3.2123: Convert to high volume low pressure (hvlp) paint guns $5,480 $1,710 - - - $5,480
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,310 $750 $470
10,050
kWh
$840
-
kW-mo/yr
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $780 $50 $355
7,560
kWh
$425
-
kW-mo/yr
- -
07 2.4314: Use synthetic lubricant $665 $450 $230
4,840
kWh
$435
-
kW-mo/yr
- -
08 2.7135: Install occupancy sensors $360 $260 $360
7,655
kWh
- - -
09 2.7134: Use photocell controls $170 $50 $100
2,070
kWh
$70
-
kW-mo/yr
- -
10 2.1131: Repair faulty insulation in furnaces, boilers, etc $86 $179 - - $86
-
MMBtu
-
TOTAL RECOMMENDED $49,446 $55,524 $10,455
222,515
kWh
$32,760
-
kW-mo/yr
$86
-
MMBtu
$6,145
TOTAL IMPLEMENTED $21,201 $18,904 $9,295
197,900
kWh
$11,155
-
kW-mo/yr
$86
-
MMBtu
$665
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs