Assessment Year | 2021 |
---|---|
Principal Product | Vodka |
NAICS | 312140: Distilleries |
SIC | 2085: Distilled and Blended Liquors |
Sales Range | $50 M to 100M |
# of Employees | 56 |
Plant Area |
195,000
ft2
|
Annual Production | 2,400
Tgal
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $74,651 | 1,082,796 |
kWh
|
$0.069 | |
Electricity Demand | $9,018 | 2,668 |
kW-mo/yr
|
$3.38 | |
Electricity Fees | $10,632 | - |
|
- | |
Natural Gas | $27,454 | 3,434 |
MMBtu
|
$7.99 | |
Waste Disposal Costs | |||||
Water Usage | $61,644 | 4,587 |
Tgal
|
$13.44 | |
TOTAL YEARLY COSTS | $183,399 | ||||
RECOMMENDED SAVINGS* | $62,141 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $62,141 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $41,395 | $5,000 | - | - | $8,279 | - | - | $33,116 | |
02 | 2.7135: Install occupancy sensors | $8,810 | $800 |
$8,810
131,690
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,591 | $6,760 |
$6,680
99,800
kWh
|
- | - | - | $(-89.0) | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,210 | $1,000 |
$1,975
29,500
kWh
|
$235
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $1,775 | - |
$1,585
23,700
kWh
|
$190
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,360 | $1,038 | - | - | - |
$1,360
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $62,141 | $14,598 |
$19,050
284,690
kWh
|
$425
-
kW-mo/yr
|
$8,279 |
$1,360
-
MMBtu
|
$(-89.0) | $33,116 | ||
TOTAL IMPLEMENTED | $62,141 | $14,598 |
$19,050
284,690
kWh
|
$425
-
kW-mo/yr
|
$8,279 |
$1,360
-
MMBtu
|
$(-89.0) | $33,116 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs