Assessment Year | 2021 |
---|---|
Principal Product | Wire rope and slings |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
90,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,141 | 792,960 |
kWh
|
$0.043 |
Electricity Demand | $19,297 | 3,442 |
kW-mo/yr
|
$5.61 |
Electricity Fees | $9,194 | - |
|
- |
TOTAL YEARLY COSTS | $62,632 | |||
RECOMMENDED SAVINGS* | $57,470 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,030 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $23,040 | $20,000 | - | - | - | $23,040 | - | - | |
02 | 2.3212: Optimize plant power factor | $4,170 | $12,500 | - |
$4,170
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $19,400 | $3,000 | - | - | $3,880 | - | - | $15,520 | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $2,950 | $200 | - | - | - | - | $2,950 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,690 | $8,520 |
$1,540
35,900
kWh
|
$1,120
-
kW-mo/yr
|
- | - | $30 | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,950 | $2,820 |
$1,140
26,330
kWh
|
$520
-
kW-mo/yr
|
- | - | $290 | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,720 | $800 |
$1,000
23,200
kWh
|
$720
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $1,210 | $140 |
$1,210
28,140
kWh
|
- | - | - | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $340 | $10 |
$210
4,870
kWh
|
$130
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $57,470 | $47,990 |
$5,100
118,440
kWh
|
$6,660
-
kW-mo/yr
|
$3,880 | $23,040 | $3,270 | $15,520 | ||
TOTAL IMPLEMENTED | $3,030 | $8,530 |
$1,750
40,770
kWh
|
$1,250
-
kW-mo/yr
|
- | - | $30 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs