| Assessment Year | 2021 |
|---|---|
| Principal Product | Thermoformed plastics |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 30 |
| Plant Area |
51,516
ft2
|
| Annual Production | 1,146
ton
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $59,435 | 1,248,640 |
kWh
|
$0.048 |
| Electricity Demand | $45,299 | 4,338 |
kW-mo/yr
|
$10.44 |
| Electricity Fees | $3,635 | - |
|
- |
| TOTAL YEARLY COSTS | $108,369 | |||
| RECOMMENDED SAVINGS* | $23,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,725 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $9,070 | $14,280 | - |
$9,070
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,260 | $2,000 |
$2,760
57,700
kWh
|
$4,500
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,370 | $6,880 |
$670
14,050
kWh
|
$1,085
-
kW-mo/yr
|
- | $615 | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,380 | $13 |
$900
18,850
kWh
|
$1,480
-
kW-mo/yr
|
- | - | |
| 05 | 2.8123: Pay utility bills on time | $1,735 | - | - | - | $1,735 | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $980 | $1,040 |
$980
20,500
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $23,795 | $24,213 |
$5,310
111,100
kWh
|
$16,135
-
kW-mo/yr
|
$1,735 | $615 | ||
| TOTAL IMPLEMENTED | $14,725 | $9,933 |
$5,310
111,100
kWh
|
$7,065
-
kW-mo/yr
|
$1,735 | $615 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs