Assessment Year | 2020 |
---|---|
Principal Product | Truck mounted aerial lift platforms |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
204,000
ft2
|
Annual Production | 3,500
pieces
|
Production Hrs. Annual | 4,794
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,721 | 4,115,115 |
kWh
|
$0.049 |
Electricity Demand | $104,755 | 12,741 |
kW-mo/yr
|
$8.22 |
Electricity Fees | $24,980 | - |
|
- |
Natural Gas | $51,740 | 9,460 |
MMBtu
|
$5.47 |
TOTAL YEARLY COSTS | $383,196 | |||
RECOMMENDED SAVINGS* | $149,095 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,135 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $124,900 | $15,000 | - | - | $24,980 | - | $99,920 | |
02 | 2.3212: Optimize plant power factor | $11,260 | $16,200 | - |
$11,260
-
kW-mo/yr
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $11,800 | - | - | - | - |
$11,800
-
MMBtu
|
- | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $630 | $100 |
$400
8,800
kWh
|
$230
-
kW-mo/yr
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $505 | $13 |
$330
7,300
kWh
|
$175
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $149,095 | $31,313 |
$730
16,100
kWh
|
$11,665
-
kW-mo/yr
|
$24,980 |
$11,800
-
MMBtu
|
$99,920 | ||
TOTAL IMPLEMENTED | $1,135 | $113 |
$730
16,100
kWh
|
$405
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs