ITAC Assessment: AM0804
ITAC logo
ITAC Assessment: AM0804
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Truck mounted aerial lift platforms
NAICS 333120: Construction Machinery Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 204,000
ft2
Annual Production 3,500
pieces
Production Hrs. Annual 4,794
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,721 4,115,115
kWh
Electricity Demand $104,755 12,741
kW-mo/yr
Electricity Fees $24,980 -
Natural Gas $51,740 9,460
MMBtu
TOTAL YEARLY COSTS $383,196
RECOMMENDED SAVINGS* $149,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,135

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $124,900 $15,000 - - $24,980 - $99,920
02 2.3212: Optimize plant power factor $11,260 $16,200 - $11,260
-
kW-mo/yr
- - -
03 2.6218: Turn off equipment when not in use $11,800 - - - - $11,800
-
MMBtu
-
04 2.7111: Reduce illumination to minimum necessary levels $630 $100 $400
8,800
kWh
$230
-
kW-mo/yr
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $505 $13 $330
7,300
kWh
$175
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $149,095 $31,313 $730
16,100
kWh
$11,665
-
kW-mo/yr
$24,980 $11,800
-
MMBtu
$99,920
TOTAL IMPLEMENTED $1,135 $113 $730
16,100
kWh
$405
-
kW-mo/yr
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs