Assessment Year | 2019 |
---|---|
Principal Product | Plastic containers, buckets, and material handling products |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
108,000
ft2
|
Annual Production | 36,000,000
pieces
|
Production Hrs. Annual | 8,664
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,240,810 | 18,654,404 |
kWh
|
$0.067 | |
Electricity Demand | $327,670 | 37,998 |
kW-mo/yr
|
$8.62 | |
Electricity Fees | $47,631 | - |
|
- | |
Natural Gas | $4,996 | 1,058 |
MMBtu
|
$4.72 | |
Waste Disposal Costs | |||||
Water Usage | $25,152 | 6,293 |
Tgal
|
$4.00 | |
Water Disposal | $29,904 | 6,293 |
Tgal
|
$4.75 | |
TOTAL YEARLY COSTS | $1,676,163 | ||||
RECOMMENDED SAVINGS* | $384,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $380,485 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $282,870 | $5,000 | - | - | - | $282,870 | - | - | |
02 | 2.8121: Apply for tax-free status for energy purchases | $56,640 | $5,000 | - | - | - | - | - | $56,640 | |
03 | 2.3212: Optimize plant power factor | $40,100 | $66,545 | - |
$40,100
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $2,180 | $1,670 |
$2,180
46,330
kWh
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,725 | $2,590 |
$1,380
29,300
kWh
|
$320
-
kW-mo/yr
|
- | - | $25 | - | |
06 | 2.8123: Pay utility bills on time | $540 | - | - | - | $540 | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $335 | $8 |
$275
5,900
kWh
|
$60
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $384,390 | $80,813 |
$3,835
81,530
kWh
|
$40,480
-
kW-mo/yr
|
$540 | $282,870 | $25 | $56,640 | ||
TOTAL IMPLEMENTED | $380,485 | $76,553 |
$275
5,900
kWh
|
$40,160
-
kW-mo/yr
|
$540 | $282,870 | - | $56,640 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs