Assessment Year | 2019 |
---|---|
Principal Product | Clay coated and chip paperboard |
NAICS | 322130: Paperboard Mills |
SIC | 2631: Paperboard Mills |
Sales Range | $50 M to 100M |
# of Employees | 95 |
Plant Area |
170,000
ft2
|
Annual Production | 124,000
units
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,338,100 | 55,519,380 |
kWh
|
$0.042 |
Electricity Demand | $735,222 | 97,780 |
kW-mo/yr
|
$7.52 |
Electricity Fees | $3,140,978 | - |
|
- |
Natural Gas | $1,927,192 | 1,280,254 |
MMBtu
|
$1.51 |
TOTAL YEARLY COSTS | $8,141,493 | |||
RECOMMENDED SAVINGS* | $747,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $144,579 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3321: Use steam pressure reduction to generate power | $290,927 | $1,011,274 |
$290,927
8,241,552
kWh
|
- | - | |
02 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $312,044 | $849,614 |
$312,044
6,915,582
kWh
|
- | - | |
03 | 2.2113: Repair or replace steam traps | $56,595 | $10,440 | - | - |
$56,595
-
MMBtu
|
|
04 | 2.4314: Use synthetic lubricant | $13,271 | $14,560 |
$10,525
250,589
kWh
|
$2,746
-
kW-mo/yr
|
- | |
05 | 2.3212: Optimize plant power factor | $70,814 | $178,864 | - |
$70,814
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,322 | $825 |
$2,322
55,287
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,577 | $2,640 |
$1,036
24,672
kWh
|
$541
-
kW-mo/yr
|
- | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $399 | $280 |
$264
6,284
kWh
|
$135
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $747,949 | $2,068,497 |
$617,118
15,493,966
kWh
|
$74,236
-
kW-mo/yr
|
$56,595
-
MMBtu
|
||
TOTAL IMPLEMENTED | $144,579 | $207,329 |
$13,883
330,548
kWh
|
$74,101
-
kW-mo/yr
|
$56,595
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs