| Assessment Year | 2019 |
|---|---|
| Principal Product | Building fasteners and closures |
| NAICS | 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing |
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $50 M to 100M |
| # of Employees | 165 |
| Plant Area |
205,000
ft2
|
| Annual Production | 9,600,000,000
pieces
|
| Production Hrs. Annual | 3,980
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $276,202 | 7,383,130 |
kWh
|
$0.037 | |
| Electricity Demand | $240,365 | 27,699 |
kW-mo/yr
|
$8.68 | |
| Electricity Fees | $47,840 | - |
|
- | |
| Natural Gas | $10,765 | 1,486 |
MMBtu
|
$7.24 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $99,000 | 1,800 |
gal
|
$55.00 | |
| TOTAL YEARLY COSTS | $674,172 | ||||
| RECOMMENDED SAVINGS* | $45,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $21,635 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $19,800 | $750 | - | - |
$19,800
-
gal
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,450 | $18,920 |
$4,900
132,500
kWh
|
$3,550
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,880 | $2,000 |
$4,620
124,900
kWh
|
$3,260
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $4,685 | $6,865 | - |
$4,685
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,470 | $460 |
$210
5,710
kWh
|
$60
-
kW-mo/yr
|
- | $1,200 | |
| 06 | 2.3212: Optimize plant power factor | $1,340 | $5,250 | - |
$1,340
-
kW-mo/yr
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,160 | $650 |
$1,160
31,200
kWh
|
- | - | - | |
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $620 | $20 |
$380
10,300
kWh
|
$240
-
kW-mo/yr
|
- | - | |
| 09 | 2.7145: Install skylights | $440 | - |
$1,160
31,300
kWh
|
- | - | $(-720.0) | |
| TOTAL RECOMMENDED | $45,845 | $34,915 |
$12,430
335,910
kWh
|
$13,135
-
kW-mo/yr
|
$19,800
-
gal
|
$480 | ||
| TOTAL IMPLEMENTED | $21,635 | $27,805 |
$9,900
267,700
kWh
|
$11,735
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs