Assessment Year | 2019 |
---|---|
Principal Product | Motors and control systems |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $100 M to 500M |
# of Employees | 260 |
Plant Area |
481,000
ft2
|
Annual Production | 325
pieces
|
Production Hrs. Annual | 4,416
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $638,547 | 15,467,372 |
kWh
|
$0.041 | |
Electricity Demand | $261,017 | 35,467 |
kW-mo/yr
|
$7.36 | |
Electricity Fees | $20,337 | - |
|
- | |
Natural Gas | $21,616 | 6,511 |
MMBtu
|
$3.32 | |
Waste Disposal Costs | |||||
Water Disposal | $2,500 | 4,100 |
Tgal
|
$0.61 | |
TOTAL YEARLY COSTS | $944,017 | ||||
RECOMMENDED SAVINGS* | $24,818 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $11,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,460 | $16,000 |
$4,870
118,700
kWh
|
$2,590
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,000 | $8,765 |
$3,240
79,000
kWh
|
$1,760
-
kW-mo/yr
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,160 | - |
$692
16,884
kWh
|
$2,468
-
kW-mo/yr
|
- | |
04 | 2.4314: Use synthetic lubricant | $3,033 | - |
$1,976
48,190
kWh
|
$1,057
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,795 | $1,000 |
$1,830
44,600
kWh
|
$965
-
kW-mo/yr
|
- | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,880 | $6,600 |
$(-380.0)
(-9,340)
kWh
|
- |
$2,260
-
Tgal
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,380 | $3,300 |
$900
22,050
kWh
|
$480
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $110 | $240 |
$110
2,680
kWh
|
- | - | |
TOTAL RECOMMENDED | $24,818 | $35,905 |
$13,238
322,764
kWh
|
$9,320
-
kW-mo/yr
|
$2,260
-
Tgal
|
||
TOTAL IMPLEMENTED | $11,635 | $20,300 |
$7,600
185,350
kWh
|
$4,035
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs