| Assessment Year | 2018 |
|---|---|
| Principal Product | Bronze valves and fittings |
| NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
| SIC | 3492: Fluid Power Valves and Hose Fittings |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
200,000
ft2
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 4,032
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $433,348 | 13,073,422 |
kWh
|
$0.033 | |
| Electricity Demand | $246,970 | 38,638 |
kW-mo/yr
|
$6.39 | |
| Electricity Fees | $15,546 | - |
|
- | |
| Natural Gas | $61,667 | 12,440 |
MMBtu
|
$4.96 | |
| Waste Disposal Costs | |||||
| Solid Waste (non-haz) | $128,000 | 1,535,000 |
lb
|
$0.083 | |
| TOTAL YEARLY COSTS | $885,531 | ||||
| RECOMMENDED SAVINGS* | $82,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $38,530 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $26,170 | $10,000 |
$17,540
531,500
kWh
|
$8,630
-
kW-mo/yr
|
- | - | |
| 02 | 2.3212: Optimize plant power factor | $20,800 | $48,700 | - |
$20,800
-
kW-mo/yr
|
- | - | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $17,710 | $5,110 |
$(-1,060.0)
(-32,240)
kWh
|
$(-770.0)
-
kW-mo/yr
|
$19,540
-
lb
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,360 | $32,745 |
$8,285
251,000
kWh
|
$4,075
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,840 | $12 |
$2,460
74,540
kWh
|
$1,380
-
kW-mo/yr
|
- | - | |
| 06 | 3.7132: Reuse rags until completely soiled | $1,520 | - | - | - | - | $1,520 | |
| TOTAL RECOMMENDED | $82,400 | $96,567 |
$27,225
824,800
kWh
|
$34,115
-
kW-mo/yr
|
$19,540
-
lb
|
$1,520 | ||
| TOTAL IMPLEMENTED | $38,530 | $42,745 |
$25,825
782,500
kWh
|
$12,705
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs