| Assessment Year | 2018 |
|---|---|
| Principal Product | foamglass insulation |
| NAICS | 327211: Flat Glass Manufacturing |
| SIC | 3211: Flat Glass |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
76,487
ft2
|
| Annual Production | 17,170
thousand feet
|
| Production Hrs. Annual | 7,899
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $342,148 | 8,530,662 |
kWh
|
$0.040 |
| Electricity Demand | $202,959 | 20,457 |
kW-mo/yr
|
$9.92 |
| Electricity Fees | $1,987 | - |
|
- |
| Natural Gas | $288,463 | 78,591 |
MMBtu
|
$3.67 |
| TOTAL YEARLY COSTS | $835,557 | |||
| RECOMMENDED SAVINGS* | $264,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $83,840 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $173,300 | $721,800 |
$126,500
3,167,000
kWh
|
$78,400
-
kW-mo/yr
|
$(-31,600.0) | - | |
| 02 | 2.3212: Optimize plant power factor | $71,530 | $81,610 | - |
$71,530
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,060 | $1,000 |
$5,590
139,800
kWh
|
$3,470
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,210 | $22 |
$3,960
99,000
kWh
|
$3,250
-
kW-mo/yr
|
- | - | |
| 05 | 2.8121: Apply for tax-free status for energy purchases | $2,740 | - | - | - | - | $2,740 | |
| 06 | 2.7135: Install occupancy sensors | $510 | $595 |
$240
5,950
kWh
|
$270
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $264,350 | $805,027 |
$136,290
3,411,750
kWh
|
$156,920
-
kW-mo/yr
|
$(-31,600.0) | $2,740 | ||
| TOTAL IMPLEMENTED | $83,840 | $83,205 |
$5,830
145,750
kWh
|
$75,270
-
kW-mo/yr
|
- | $2,740 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs