Assessment Year | 2018 |
---|---|
Principal Product | Precision machine parts |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
60,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 7,968
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $133,800 | 2,308,680 |
kWh
|
$0.058 | |
Electricity Demand | $51,084 | 5,326 |
kW-mo/yr
|
$9.59 | |
Natural Gas | $19,257 | 2,531 |
MMBtu
|
$7.61 | |
Waste Disposal Costs | |||||
Other Liquid (non-haz) | $87,100 | 130,000 |
gal
|
$0.67 | |
TOTAL YEARLY COSTS | $291,241 | ||||
RECOMMENDED SAVINGS* | $108,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $97,895 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.6192: Use a less expensive method of waste removal | $79,100 | $11,000 | - | - |
$(-1,210.0)
-
MMBtu
|
$80,310
-
gal
|
- | - | - | |
02 | 4.611: Begin a practice of predictive / preventative maintenance | $9,150 | $4,570 |
$1,980
33,200
kWh
|
$620
-
kW-mo/yr
|
- | - | $6,550 | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,590 | $6,500 |
$4,790
82,000
kWh
|
$800
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.3212: Optimize plant power factor | $5,140 | $9,860 | - |
$5,140
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,750 | $980 |
$1,750
29,900
kWh
|
- | - | - | - | - | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $7,385 | $1,500 | - | - | - | - | - | $1,837 | $5,548 | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $680 | $40 |
$480
8,270
kWh
|
$200
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $108,795 | $34,450 |
$9,000
153,370
kWh
|
$6,760
-
kW-mo/yr
|
$(-1,210.0)
-
MMBtu
|
$80,310
-
gal
|
$6,550 | $1,837 | $5,548 | ||
TOTAL IMPLEMENTED | $97,895 | $28,900 |
$5,270
90,270
kWh
|
$6,140
-
kW-mo/yr
|
$(-1,210.0)
-
MMBtu
|
$80,310
-
gal
|
- | $1,837 | $5,548 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs