ITAC Assessment: AM0747
ITAC logo
ITAC Assessment: AM0747
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Turkeys
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $100
M
to 500
M
# of Employees 700
Plant Area 330,000
ft2
Annual Production 140,000,000
lb
Production Hrs. Annual 5,952
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,139,032 40,599,125
kWh
Electricity Demand $551,697 76,577
kW-mo/yr
Electricity Fees $34,250 -
Natural Gas $342,150 121,991
MMBtu
Waste Disposal Costs
Water Usage $644,777 278,380
Tgal
Water Disposal $867,997 278,380
Tgal
TOTAL YEARLY COSTS $3,579,903
RECOMMENDED SAVINGS* $274,420 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2622: Replace existing chiller with high efficiency model $170,240 $376,350 $126,600
4,219,900
kWh
$43,640
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $56,800 $121,500 $56,800
1,893,300
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $29,900 $44,160 $19,800
661,200
kWh
$10,100
-
kW-mo/yr
04 2.3212: Optimize plant power factor $12,800 $39,100 - $12,800
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $4,680 $30 $3,100
103,300
kWh
$1,580
-
kW-mo/yr
TOTAL RECOMMENDED $274,420 $581,140 $206,300
6,877,700
kWh
$68,120
-
kW-mo/yr
TOTAL IMPLEMENTED $99,500 $204,760 $76,600
2,554,500
kWh
$22,900
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs