Assessment Year | 2018 |
---|---|
Principal Product | Milk and dairy products |
NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
100,000
ft2
|
Annual Production | 41,800
Tgal
|
Production Hrs. Annual | 4,960
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $551,202 | 9,534,329 |
kWh
|
$0.058 |
Electricity Demand | $229,076 | 28,936 |
kW-mo/yr
|
$7.92 |
Electricity Fees | $17,195 | - |
|
- |
Natural Gas | $145,223 | 40,828 |
MMBtu
|
$3.56 |
TOTAL YEARLY COSTS | $942,696 | |||
RECOMMENDED SAVINGS* | $34,336 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $4,100 | $6,700 | - |
$4,100
-
kW-mo/yr
|
- | |
02 | 2.3212: Optimize plant power factor | $4,300 | $8,300 | - |
$4,300
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,080 | $13 |
$9,100
95,000
kWh
|
$1,980
-
kW-mo/yr
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $10,440 | $1,025 |
$10,440
109,000
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $865 | $3,190 |
$710
7,400
kWh
|
$155
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,570 | $1,820 |
$1,570
16,400
kWh
|
- | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,701 | - |
$1,365
14,252
kWh
|
$336
-
kW-mo/yr
|
- | |
08 | 2.2163: Use minimum steam operating pressure | $280 | $13 | - | - |
$280
-
MMBtu
|
|
TOTAL RECOMMENDED | $34,336 | $21,061 |
$23,185
242,052
kWh
|
$10,871
-
kW-mo/yr
|
$280
-
MMBtu
|
||
TOTAL IMPLEMENTED | $32,635 | $21,061 |
$21,820
227,800
kWh
|
$10,535
-
kW-mo/yr
|
$280
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs