Assessment Year | 2017 |
---|---|
Principal Product | Tortillas |
NAICS | 311830: Tortilla Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
95,000
ft2
|
Annual Production | 22,000,000
lb
|
Production Hrs. Annual | 3,096
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,593 | 2,114,100 |
kWh
|
$0.057 |
Electricity Demand | $53,753 | 5,948 |
kW-mo/yr
|
$9.04 |
Electricity Fees | $262 | - |
|
- |
Natural Gas | $196,250 | 45,826 |
MMBtu
|
$4.28 |
TOTAL YEARLY COSTS | $370,858 | |||
RECOMMENDED SAVINGS* | $65,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,800 | $35,500 |
$15,400
270,300
kWh
|
$3,400
-
kW-mo/yr
|
- | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $18,400 | - | - | - |
$18,400
-
MMBtu
|
|
03 | 2.6218: Turn off equipment when not in use | $10,300 | $1,940 |
$10,300
180,100
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,610 | $120 |
$5,530
97,700
kWh
|
$2,080
-
kW-mo/yr
|
- | |
05 | 2.3212: Optimize plant power factor | $4,070 | $6,200 | - |
$4,070
-
kW-mo/yr
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,360 | $710 |
$1,940
34,100
kWh
|
$420
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,210 | $3,600 |
$1,810
31,800
kWh
|
$400
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $830 | $2,000 |
$830
14,500
kWh
|
- | - | |
09 | 2.4239: Eliminate or reduce compressed air usage | $590 | $475 |
$590
10,300
kWh
|
- | - | |
TOTAL RECOMMENDED | $65,170 | $50,545 |
$36,400
638,800
kWh
|
$10,370
-
kW-mo/yr
|
$18,400
-
MMBtu
|
||
TOTAL IMPLEMENTED | $42,600 | $41,810 |
$19,980
350,700
kWh
|
$4,220
-
kW-mo/yr
|
$18,400
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs