ITAC Assessment: AM0735
ITAC logo
ITAC Assessment: AM0735
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Trenchers
NAICS 333923: Overhead Traveling Crane, Hoist, and Monorail System Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area 100,000
ft2
Annual Production 12
units
Production Hrs. Annual 2,500
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,946 1,206,100
kWh
Electricity Demand $54,190 5,412
kW-mo/yr
Electricity Fees $667 -
LPG $8,493 425
MMBtu
TOTAL YEARLY COSTS $115,296
RECOMMENDED SAVINGS* $33,600 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,165

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $18,250 $52,360 $9,450
210,000
kWh
$8,800
-
kW-mo/yr
- -
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $8,320 $4,120 - - - $8,320
03 2.7124: Make a practice of turning off lights when not needed $2,770 $320 $1,630
36,200
kWh
$1,140
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $920 $1,700 $920
20,500
kWh
- - -
05 3.7132: Reuse rags until completely soiled $880 - - - - $880
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,160 $500 $575
12,800
kWh
$585
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,105 $410 $95
2,145
kWh
$25
-
kW-mo/yr
$985 -
08 2.4231: Reduce the pressure of compressed air to the minimum required $195 $15 $95
2,100
kWh
$100
-
kW-mo/yr
- -
TOTAL RECOMMENDED $33,600 $59,425 $12,765
283,745
kWh
$10,650
-
kW-mo/yr
$985 $9,200
TOTAL IMPLEMENTED $24,165 $53,590 $11,750
261,145
kWh
$10,550
-
kW-mo/yr
$985 $880
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs