| Assessment Year | 2017 |
|---|---|
| Principal Product | Mechanical cable controls and pedals for industrial applications |
| NAICS | 335314: Relay and Industrial Control Manufacturing |
| SIC | 3625: Relays and Industrial Controls |
| Sales Range | $10 M to 50M |
| # of Employees | 109 |
| Plant Area |
78,000
ft2
|
| Annual Production | 12,000,000
pieces
|
| Production Hrs. Annual | 2,008
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $88,082 | 1,659,146 |
kWh
|
$0.053 |
| Electricity Demand | $57,438 | 5,093 |
kW-mo/yr
|
$11.28 |
| Electricity Fees | $3,825 | - |
|
- |
| Natural Gas | $1,824 | 282 |
MMBtu
|
$6.47 |
| TOTAL YEARLY COSTS | $151,169 | |||
| RECOMMENDED SAVINGS* | $28,635 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,865 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $6,900 | - | - | - |
$6,900
-
lb
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,965 | $28,840 |
$4,815
96,300
kWh
|
$6,150
-
kW-mo/yr
|
- | |
| 03 | 2.3212: Optimize plant power factor | $3,490 | $3,740 | - |
$3,490
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,930 | $1,000 |
$1,200
24,100
kWh
|
$1,730
-
kW-mo/yr
|
- | |
| 05 | 2.2511: Insulate bare equipment | $3,770 | $1,000 |
$1,540
30,800
kWh
|
$2,230
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $580 | $220 |
$580
11,675
kWh
|
- | - | |
| TOTAL RECOMMENDED | $28,635 | $34,800 |
$8,135
162,875
kWh
|
$13,600
-
kW-mo/yr
|
$6,900
-
lb
|
||
| TOTAL IMPLEMENTED | $24,865 | $33,800 |
$6,595
132,075
kWh
|
$11,370
-
kW-mo/yr
|
$6,900
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs