Assessment Year | 2017 |
---|---|
Principal Product | HDPE Blow molded containers |
NAICS | 326160: Plastics Bottle Manufacturing |
SIC | 3085: Plastics Bottles |
Sales Range | $50 M to 100M |
# of Employees | 60 |
Plant Area |
200,000
ft2
|
Annual Production | 16,400,000
lb
|
Production Hrs. Annual | 6,072
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $209,727 | 5,093,969 |
kWh
|
$0.041 |
Electricity Demand | $100,140 | 11,150 |
kW-mo/yr
|
$8.98 |
Electricity Fees | $6,794 | - |
|
- |
Natural Gas | $8,010 | 1,421 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | $324,671 | |||
RECOMMENDED SAVINGS* | $24,851 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,141 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $12,300 | $16,500 | - |
$12,300
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,720 | - |
$2,620
64,000
kWh
|
$1,100
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $4,040 | $1,010 |
$4,040
98,500
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,040 | $4,690 |
$1,460
35,600
kWh
|
$580
-
kW-mo/yr
|
- | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $1,020 | - |
$650
15,900
kWh
|
$370
-
kW-mo/yr
|
- | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $1,370 | $2,000 | - | - |
$610
-
MMBtu
|
$760 | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $235 | $200 |
$165
4,000
kWh
|
$70
-
kW-mo/yr
|
- | - | |
08 | 2.2511: Insulate bare equipment | $126 | $210 |
$90
2,200
kWh
|
$36
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $24,851 | $24,610 |
$9,025
220,200
kWh
|
$14,456
-
kW-mo/yr
|
$610
-
MMBtu
|
$760 | ||
TOTAL IMPLEMENTED | $7,141 | $5,100 |
$4,985
121,700
kWh
|
$2,156
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs