| Assessment Year | 2016 |
|---|---|
| Principal Product | Pumps and process systems |
| NAICS | 333911: Pump and Pumping Equipment Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 135 |
| Plant Area |
125,000
ft2
|
| Annual Production | 75
units
|
| Production Hrs. Annual | 5,166
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $114,217 | 1,480,720 |
kWh
|
$0.077 | |
| Electricity Demand | $77,815 | 8,092 |
kW-mo/yr
|
$9.62 | |
| Electricity Fees | $1,782 | - |
|
- | |
| Natural Gas | $23,222 | 4,745 |
MMBtu
|
$4.89 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $105,908 | 913 |
gal
|
$116.00 | |
| TOTAL YEARLY COSTS | $322,944 | ||||
| RECOMMENDED SAVINGS* | $88,370 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $48,140 | $2,710 | - | - |
$48,140
-
gal
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,510 | $46,840 |
$16,840
320,750
kWh
|
$7,670
-
kW-mo/yr
|
- | - | |
| 03 | 2.3212: Optimize plant power factor | $11,700 | $26,740 | - |
$11,700
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,710 | $30 |
$1,770
33,730
kWh
|
$940
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $450 | $200 |
$310
5,990
kWh
|
$140
-
kW-mo/yr
|
- | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $400 | - |
$260
4,980
kWh
|
$140
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $350 | $150 |
$40
720
kWh
|
$10
-
kW-mo/yr
|
- | $300 | |
| 08 | 2.7232: Replace existing hvac unit with high efficiency model | $110 | $280 |
$60
1,180
kWh
|
$50
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $88,370 | $76,950 |
$19,280
367,350
kWh
|
$20,650
-
kW-mo/yr
|
$48,140
-
gal
|
$300 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs