Assessment Year | 2016 |
---|---|
Principal Product | Rubber |
NAICS | 325212: Synthetic Rubber Manufacturing |
SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
Sales Range | $50 M to 100M |
# of Employees | 158 |
Plant Area |
500,000
ft2
|
Annual Production | 180,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,627,170 | 57,969,000 |
kWh
|
$0.045 |
Electricity Demand | $746,039 | 107,676 |
kW-mo/yr
|
$6.93 |
Electricity Fees | $159,536 | - |
|
- |
Natural Gas | $2,834,335 | 934,532 |
MMBtu
|
$3.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $927,610 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $880,910 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $515,000 | $75,000 | - | - | - |
$515,000
-
MMBtu
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $195,000 | $2,000 | - | - | - |
$195,000
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $73,125 | $105,700 |
$56,605
1,048,310
kWh
|
$11,780
-
kW-mo/yr
|
- | - | $4,740 | |
04 | 2.8123: Pay utility bills on time | $57,500 | - | - | - | $57,500 | - | - | |
05 | 2.3212: Optimize plant power factor | $36,800 | $61,950 | - |
$36,800
-
kW-mo/yr
|
- | - | - | |
06 | 2.4314: Use synthetic lubricant | $35,540 | - |
$29,400
544,403
kWh
|
$6,140
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,900 | $22,740 |
$8,410
155,676
kWh
|
$1,490
-
kW-mo/yr
|
- | - | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $3,420 | $210 |
$2,830
52,390
kWh
|
$590
-
kW-mo/yr
|
- | - | - | |
09 | 2.2511: Insulate bare equipment | $1,325 | $1,200 | - | - | - |
$1,325
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $927,610 | $268,800 |
$97,245
1,800,779
kWh
|
$56,800
-
kW-mo/yr
|
$57,500 |
$711,325
-
MMBtu
|
$4,740 | ||
TOTAL IMPLEMENTED | $880,910 | $184,110 |
$88,835
1,645,103
kWh
|
$18,510
-
kW-mo/yr
|
$57,500 |
$711,325
-
MMBtu
|
$4,740 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs