Assessment Year | 2015 |
---|---|
Principal Product | Pewter and zinc alloy emblems |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
90,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 2,690
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,355 | 648,720 |
kWh
|
$0.053 |
Electricity Demand | $10,922 | 1,969 |
kW-mo/yr
|
$5.55 |
Natural Gas | $2,144 | 238 |
MMBtu
|
$9.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,650 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,400 | $9,800 | - | - | - | $8,400 | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $1,650 | $580 |
$985
18,410
kWh
|
$455
-
kW-mo/yr
|
- | $210 | |
03 | 2.6123: Remove unneeded service lines to eliminate potential leaks | $1,225 | - | - | - |
$1,225
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $125 | $30 |
$85
1,560
kWh
|
$40
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $100 | $140 |
$95
1,765
kWh
|
$5
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $11,500 | $10,550 |
$1,165
21,735
kWh
|
$500
-
kW-mo/yr
|
$1,225
-
MMBtu
|
$8,610 | ||
TOTAL IMPLEMENTED | $1,650 | $580 |
$985
18,410
kWh
|
$455
-
kW-mo/yr
|
- | $210 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs