Assessment Year | 2015 |
---|---|
Principal Product | extruded aluminum products |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
100,000
ft2
|
Annual Production | 16,000,000
lb
|
Production Hrs. Annual | 6,072
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $217,211 | 4,201,380 |
kWh
|
$0.052 |
Electricity Demand | $96,559 | 9,965 |
kW-mo/yr
|
$9.69 |
Electricity Fees | $2,169 | - |
|
- |
Natural Gas | $109,825 | 36,888 |
MMBtu
|
$2.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,362 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $12,970 | $10,000 |
$9,380
181,390
kWh
|
$3,590
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,830 | $5,000 |
$8,630
166,880
kWh
|
$3,200
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,880 | $16,750 |
$7,220
139,600
kWh
|
$2,660
-
kW-mo/yr
|
- | |
04 | 2.8114: Change rate schedules or other changes in utility service | $2,124 | - | - | - |
$2,124
-
MMBtu
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,115 | - |
$1,225
23,670
kWh
|
$890
-
kW-mo/yr
|
- | |
06 | 2.4314: Use synthetic lubricant | $1,560 | - |
$860
16,640
kWh
|
$700
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $870 | $6 |
$530
10,230
kWh
|
$340
-
kW-mo/yr
|
- | |
08 | 2.7122: Disconnect ballasts | $533 | $1,100 |
$387
7,481
kWh
|
$146
-
kW-mo/yr
|
- | |
09 | 2.7124: Make a practice of turning off lights when not needed | $480 | $10 |
$320
6,220
kWh
|
$160
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $42,362 | $32,866 |
$28,552
552,111
kWh
|
$11,686
-
kW-mo/yr
|
$2,124
-
MMBtu
|
||
TOTAL IMPLEMENTED | $42,362 | $32,866 |
$28,552
552,111
kWh
|
$11,686
-
kW-mo/yr
|
$2,124
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs