Assessment Year | 2015 |
---|---|
Principal Product | Centrifugal castings |
NAICS | 331513: Steel Foundries (except Investment) |
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
50,000
ft2
|
Annual Production | 5,500,000
lb
|
Production Hrs. Annual | 2,772
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $172,458 | 3,525,916 |
kWh
|
$0.049 |
Electricity Demand | $142,012 | 22,913 |
kW-mo/yr
|
$6.20 |
Electricity Fees | $8,695 | - |
|
- |
Natural Gas | $162,239 | 29,887 |
MMBtu
|
$5.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,466 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,436 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.4116: Meter recycled water (to reduce sewer charges) | $6,985 | $2,000 | - | - |
$6,985
-
Tgal
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,480 | $1,000 |
$2,900
63,200
kWh
|
$2,580
-
kW-mo/yr
|
- | - | |
03 | 2.6242: Minimize operation of equipment maintained in standby condition | $4,320 | $5,400 |
$3,780
82,231
kWh
|
$540
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,295 | $7,280 |
$2,650
57,577
kWh
|
$1,645
-
kW-mo/yr
|
- | - | |
05 | 2.4322: Use or replace with energy efficient substitutes | $1,840 | $1,790 |
$1,840
39,920
kWh
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $585 | $5 |
$310
6,770
kWh
|
$275
-
kW-mo/yr
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $430 | - |
$430
9,400
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $211 | $75 |
$46
1,000
kWh
|
$10
-
kW-mo/yr
|
- | $155 | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $170 | $200 |
$110
2,340
kWh
|
$60
-
kW-mo/yr
|
- | - | |
10 | 2.7124: Make a practice of turning off lights when not needed | $150 | - |
$95
2,070
kWh
|
$55
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $24,466 | $17,750 |
$12,161
264,508
kWh
|
$5,165
-
kW-mo/yr
|
$6,985
-
Tgal
|
$155 | ||
TOTAL IMPLEMENTED | $8,436 | $3,070 |
$5,301
115,300
kWh
|
$2,980
-
kW-mo/yr
|
- | $155 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs